Build: #487 failed Manual run from the stage: Release by Rafal Korytkowski
Build result summary
Details
- Completed
- Queue duration
- < 1 second
- Duration
- 174 minutes
- Labels
- None
- Revisions
-
- Git
-
6fc8921d1ac40c4ba7018a71292998b1d4c57f31
6fc8921d1ac40c4ba7018a71292998b1d4c57f31 - Release scripts
-
ced9ff00825ca1cb8c744547be4ba8ff994bd71b
ced9ff00825ca1cb8c744547be4ba8ff994bd71b
- Total tests
- 5071
- Fixed in
- #489 (Manual run by Rafal Korytkowski)
Tests
- 0 New failures
- 0 Existing failures
- 0 Fixed
- 2 Quarantined / skipped
Responsible
- Rafal Korytkowski Automatically assigned
Code commits
Author | Commit | Commit date | |
---|---|---|---|
Rafal Korytkowski |
6fc8921d1ac40c4ba7018a71292998b1d4c57f31
|
Jira issues
Issue | Description | Status | |
---|---|---|---|
Unknown Issue Type | FM2-572 | Could not obtain issue details from Jira |
Error summary for Release to Maven
The job generated some errors, drill down into the full build log for more details.
[ERROR] mvn release:prepare failed. Attempting to do a release rollback.
[ERROR] mvn release:prepare failed, scroll up the logs to see the error. release:rollback was attempted. Delete the tag from the repository (if it exists), check if the SCM tag is a ssh and not http and try again.